Expansion of the Glen Dhu site is planned as the site has potential for additional generation capacity. Shear Wind's intentions are to bid on an expected Request for Proposals for Renewable Energy in 2012 for a Phase II extension of this site.

Project Overview

  • Land base: 6,000 acres East of New Glasgow, N.S. Average elevation is 250m.
  • Potential Wind Farm Size: A total of 230 MW
  • Wind monitoring data indicates an above average wind resource. Wind Resource Assessment completed indicating excellent results for capacity, long term projections, and potential electricity generation.
  • Three monitoring towers continue to collect wind data for future expansion.
  • Transmission Lines transect the project area with confirmed availability for expansion.
  • Potential Phase II and Phase III are in planning and development stages.

Projects

TSX-V : SWX

Current Teras Stock Price
Last Trade ()
View Detailed Stock Information

Shear Wind News

Shear Wind Announces Change in Year End and Update on Sale of Willow Ridge Assets

January 27, 2012

Read Complete Press Release

Shear Wind Announces Management Changes; Option Grants

January 23, 2012

Read Complete Press Release

Shear Wind Reports $7.5 Million Revenue at Financial Uear End

January 9, 2012

Read Complete Press Release

Shear Wind Proposes Change in Year End

December 30, 2011

Read Complete Press Release

Shear Wind Announces Addition to Board of Directors

October 28th, 2011

Read Complete Press Release

Shear Wind Announces Director Resignation

October 24th, 2011

Read Complete Press Release

Shear Wind Announces Sale of Willow Ridge Assets and Submission of Response to Saskpower RFP

September 22nd, 2011

Read Complete Press Release